In connection with Pre Non Interlocking/Non Interlocking working for doubling of line between Donakonda - Gajjelakonda in Guntakal - Guntur section from 11th March, 2021 to 01st April, 2021, following are the changes in pattern of train services
·Train No.08463 Bhubaneswar – KSR Bengaluru Special Train leaving Bhubaneswar at 05.40 hrs of 29th, 30th, 31st March and 01st April, 2021 will be diverted via Krishna Cana, Gudur, Renigunta, Melpakkam, Katpadi and Jolarpettai route instead of Krishna Canal, Gajjelakonda , Guntakal and Dharmavaram route
·Train No.08464 KSR Bengaluru – Bhubaneswar Special Train leaving KSR Bengaluru at 13.40 hrs of 29th, 30th, 31st March and 01st April, 2021 will be diverted via Jolarpettai, Katpadi, Melpakkam, Renigunta, Gudur, Krishna Canal route instead of Dharmavaram, Guntakal, Gajjelakonda and Krishna Canal route